Set out below is the Club maintenance work performed for the week ending Saturday the 11th August 2018

7th Aug 2018 - Weed control. Spray weeds both inside courts and outside, including pathways and area between boundary fence and court fences of courts 1 and 5. Total time taken 1 hr.

8th Aug 2018 - Removing dirt and moss from under base bars from court 4, Total time to go right round all fences on court 4 , total 1.5 hrs.

9th Aug 2018 - The dirt and moss laden sand then has to be picked up and disposed of. North & east fences where done then started sand replacement. Total time taken 2 hrs

10th Aug 2018 - Rake up all leaf litter in front of court 2 and empty all external bins.. Time taken 1.5 hrs.
Total hours worked 6 hours. Hours billed to the Club 5 hrs.
Total hours worked above invoiced hours = 1 hr